CONVENTIONS
Transparent by default
Methods and conventions.
The rules every calculator in the suite is built to. Each tool's specific formula trace, worked examples and limitations are published on its own tool page.
Live tools: all ten calculators are live and each publishes its own formula trail, worked example and limitations on its tool page. The conventions below are the shared rules behind every one of them.
Canonical units
Lengths are calculated in feet, areas in square feet and volumes in cubic feet. Depth entered in inches is converted with inches ÷ 12. Cubic yards are cubic feet ÷ 27 and cubic metres are cubic feet ÷ 35.3146667. Other units are display conveniences, never the calculation basis.
No hidden rounding
Intermediate values are never rounded. Only the final purchasable package is rounded up to what a supplier actually sells, with a small deterministic tolerance so an exact boundary does not add a spurious extra bag.
Density and tonnage
Volume converts to weight only with a density you enter — in lb/ft³ or tons/yd³ (US short ton, 2,000 lb). Without a density the tonnage line reads “not calculated”, never a guess of zero.
Allowances stay separate
Waste, compaction and settlement are separate, editable and visible lines — never percentages buried inside a total. A compaction factor is a planning allowance, not an engineering formula, and loose ordered volume is shown apart from in-place volume.
Existing depth is not quietly subtracted
Where a bed already has mulch or soil, the added volume is based on max(0, desired depth − existing depth) in the same units. Nothing is subtracted without showing it.
The purchasing trail
Every tool follows the same visible trail: exact need → allowances → package rounding → leftover → delivered total, with delivery charged once per supplier order and every dollar figure a quote you typed in, labelled as an example.